Scaffolding Access Licences

Share

Scaffolding can be essential to a construction project, but the arrangements for accessing neighbouring land or airspace are often overlooked. Leaving these discussions until contractors are ready to start can create avoidable delays, additional costs and disagreements.

At Stokemont, we regularly assist property owners and developers with the preparation, negotiation and agreement of scaffolding access licences across London and England. We also advise neighbouring owners who have been approached for access, helping them understand the proposals and agree appropriate protections.

When is a scaffolding access licence required?

A scaffolding access licence records permission to use a neighbouring property for an agreed purpose and period. It can cover scaffolding erected on adjoining land, components projecting into neighbouring airspace, and access needed to erect, use and dismantle the scaffold.

The starting point is to establish whether any existing rights authorise the proposed access. Property documents may contain relevant rights, including easements, which need to be considered before deciding how to proceed. Their scope should be checked against the actual access required.

For construction projects in England and Wales, two statutory routes may also be relevant:

  • Party Wall etc. Act 1996: Section 8 provides rights of entry for the purpose of carrying out work under the Act, subject to its requirements, including notice of entry. The fact that a project involves party wall works does not give unrestricted access for every element of the development.
  • Access to Neighbouring Land Act 1992: This provides a route to apply for a court order where works are reasonably necessary to preserve a property and cannot be undertaken, or would be substantially more difficult to undertake, without access to neighbouring land. The court must also consider the effect on those affected. The Act does not itself give automatic permission to enter simply because repairs are needed.

Where no existing right or court order authorises the proposed access, permission will need to be negotiated. In those circumstances, a neighbouring owner is generally entitled to decline a request. Establishing the legal position early therefore provides a sound basis for discussions.

What should a scaffolding access licence cover?

A well-prepared licence should clearly define the permitted access, the works it supports and the protections required for the neighbouring property.

Depending on the circumstances, the matters to address include:

  • The extent of access: Drawings identifying the scaffold’s position, dimensions, projections, access routes and any areas that will become unavailable for normal use.
  • Duration and removal: A defined access period, a deadline for dismantling and removal, and a procedure for agreeing any extension.
  • Security: Appropriate measures to prevent unauthorised access, including restricted ladder access, suitable barriers and scaffold alarms where appropriate.
  • Dust and falling materials: Suitable sheeting, netting, toe boards and other protective measures selected for the work and the areas affected.
  • Protection below the scaffold: Where appropriate, protective boarding may include double boarding with an impervious layer between the boards to reduce the passage of debris to areas below. The arrangement and its loading must be considered as part of the scaffold design.
  • Design review: Clear scaffold proposals, with an independent review by a suitably competent engineer where appropriate to the complexity and risks involved.
  • Working arrangements: Agreed working hours, arrangements for maintaining access to the neighbouring property, and measures to protect privacy and minimise disruption.
  • Condition and reinstatement: A schedule of condition before access begins, arrangements for reviewing the property afterwards, and clear responsibilities for making good attributable damage.
  • Insurance and costs: Appropriate insurance provisions and agreement on any access payments, professional fees or other costs.

These protections should be tailored to the proposed scaffold. Sheeting and netting affect the loads acting on the structure and must be taken into account by those responsible for its design and erection. Adding protective measures without considering their effect on the scaffold can introduce further risks.

Access licence premiums and rental payments

Where access is being negotiated contractually, the neighbouring owner may request a payment in return for allowing use of their land or airspace. This may take the form of a fixed premium or a periodic access payment.

In our experience, these discussions should consider the duration of access, the area occupied, the effect on the neighbouring owner’s use of their property and the disruption associated with the works.

Any agreed payment should be clearly recorded, together with its payment dates and the arrangements that will apply if access is needed for longer than anticipated. Addressing these points at the outset helps both parties understand their commitments and budget accordingly.

Why early advice matters

Access requirements should be considered while the construction proposals are being developed. Discovering that scaffolding depends on a neighbour’s agreement shortly before work is due to begin can put the programme under pressure.

For owners and developers, early advice allows time to assess the proposed access, identify the parties whose agreement is needed and discuss practical alternatives where necessary. It also gives neighbouring owners a proper opportunity to review the proposals and raise concerns before contractors arrive.

For a neighbouring owner, an early review can help identify how scaffolding may affect security, privacy, access and the use of their property. Those concerns can then be addressed through clear drawings, appropriate safeguards and agreed licence terms.

Scaffolding access licence advice from Stokemont

At Stokemont, we combine practical surveying advice with experience in negotiating construction access arrangements. We help owners, developers and neighbours work through the proposed access, understand the issues affecting their properties and establish clear terms for the works.

Our aim is to support progress while ensuring that the access arrangements, protective measures and responsibilities are properly considered and documented. Where specialist legal input is needed, this can be addressed alongside the surveying and licence negotiations.

If you are planning works that require scaffolding on or over a neighbouring property, or have received a request for access to your own land or airspace, contact Stokemont to discuss how we can assist.

When Do I need an Access Licence?

When Do I need an Access Licence?

Hello and welcome to today's property surveying blog post, in today’s topic we are going to be looking over building surveying procedures and taking a look into what is an access licence. Can you access your neighbour’s land without an access licence? Firstly, let us...

read more
Access Licence FAQs

Access Licence FAQs

Today, in this instalment of our property surveying blog, we are going to be taking an in-depth and focussed look at Access Licences.   We are going to be taking a deep dive into some of the more typical questions we find ourselves asked here at Stokemont on a...

read more
Access to a Neighbour’s Land

Access to a Neighbour’s Land

The Access to Neighbouring Land Act 1992(''the Act'') allows a landowner to apply for an 'Access Order' at Court, to gain access to neighbour's land where the works are required for the preservation of the landowner's land need to carry out, if the owner of the...

read more