The Party Wall Agreement process can involve several stages, with the exact steps involved depending on factors such as the type of work being carried out and the response from the adjoining owner to the initial Party Wall Notice.
At Stokemont, we can provide building and adjoining owners with expert guidance through every stage, helping ensure the correct procedures are followed in accordance with the Party Wall etc. Act 1996.
In this guide, we’ll explain what a Party Wall Agreement is, when you need one, and what to expect at every stage of the process.
What Is a Party Wall Agreement?
A Party Wall Agreement helps ensure that works covered by the Party Wall etc. Act 1996 can proceed while protecting the rights of both the building and adjoining owner.
The steps involved in reaching an agreement can vary, with the adjoining owner’s response to the proposed works key to determining what happens next.
The process begins with the building owner serving the adjoining owner with the appropriate Party Wall Notice that outlines the proposed works. From here, the next steps will differ depending on whether the adjoining owner consents or dissents from the Notice.
Written Consent
The adjoining owner is required to provide written consent if they agree to the proposed works in the Party Wall Notice. If consent is granted, then works can proceed without the need to appoint Party Wall Surveyors or prepare a Party Wall Award, provided the relevant requirements in the Act have been met.
Party Wall Award
If the adjoining owner dissents from the proposed works, then the building owner will need to pursue a Party Wall Award. A Party Wall Award is a legally binding document outlining the terms that must be met for works to proceed, along with the rights and responsibilities of both parties throughout the process.
Some of the key things the Award may cover are:
- The hours and days when work can take place, including any restrictions on early morning, evening, or weekend working.
- The methods used to conduct certain parts of the work.
- Measures required to minimise noise, dust, and disruption, including prohibiting the use of certain equipment.
- Measures required to protect the adjoining property from damage.
- Access arrangements to the adjoining property where necessary.
- Responsibility for relevant costs.
- The procedure for dealing with any damage caused by the works.
The process of obtaining and finalising a Party Wall Award can vary depending on the circumstances and how the dispute progresses.
How to Get a Party Wall Agreement
While every Party Wall Agreement process will follow its own course, there are several key steps involved in the process.
Step 1: Check Whether the Party Wall Act Applies
Before beginning work or issuing a notice, it’s important to verify whether the Party Wall etc. Act 1996 applies in your case. The Party Wall Act typically applies when proposed works involve a shared wall or structure, building up to or astride a boundary line, or excavating close to a neighbouring property.
The specific requirements and qualifying factors, including how close works must be to a neighbouring property and the depth of any proposed excavation, are set out under the Act. As a result, not all building works will require consent or a Party Wall Agreement to proceed.
If you’re unsure whether the Act applies to your proposed works, a Party Wall Surveyor can assess your plans and advise you on your requirements and whether you need to follow the Party Wall procedures.
Step 2: Serve the Correct Party Wall Notice
Once you’ve established that the Act applies, the building owner will then need to serve a Party Wall Notice on the adjoining owner. The type of notice will depend on the nature of the proposed works.
The three main types of Party Wall Notice are:
- Party Structure Notice: This is typically required for works directly affecting an existing Party Wall or structure. It requires at least two months’ notice to be given.
- Line of Junction Notice: A Line of Junction Notice is necessary when a building owner wishes to build a new wall at or astride the boundary line. Typically, this requires at least one month’s notice.
- Notice of Adjacent Excavation: This is required for any qualifying excavation works occurring within the distances outlined in the Act, usually requiring at least one month’s notice to be given.
The Party Wall Notice should contain all the required information about the proposed works and be formally served on the adjoining owner at least one or two months before works begin, depending on the type of notice required.
Step 3: The Adjoining Owner Responds
Once the Party Wall Notice has been served, the adjoining owner has 14 days to respond. They can either provide written consent to the works or dissent, which will trigger the dispute resolution process outlined in the Party Wall etc. Act 1996.
If the adjoining owner does not respond within 14 days, this is generally considered a deemed dissent, and the process will usually require the appointment of a Party Wall Surveyor.
Step 4: Appoint a Party Wall Surveyor
If the proposed work has been dissented to, then a Party Wall Surveyor will need to be appointed to resolve matters in accordance with the Act.
In these cases, the building owner and adjoining owner can either opt to appoint a single agreed surveyor to oversee all matters, or each party can appoint their own surveyor to review the proposed works. When two surveyors are appointed, they will work together to resolve disputed matters and finalise a Party Wall Award.
Where separate surveyors are appointed, they will also select a third surveyor, who can be called on to determine disputed matters if the two surveyors can’t reach an agreement.
Step 5: Schedule of Condition and Party Wall Award
Before the Party Wall Award is finalised, a Schedule of Condition Report will often be prepared to record the condition of the adjoining property before works begin. This provides a detailed record of any existing structural damage that can be referred to if concerns or disputes arise during or after the works.
The appointed surveyor or surveyors will then work to agree on the terms of the Party Wall Award, considering the proposed works and any appropriate measures to protect the adjoining property. Once finalised, the Award is served on both owners, and the terms become legally binding.
Step 6: Works Begin
Once the Party Wall Award has been served and the relevant notice period has passed, the building owner can proceed with the planned works in line with the terms set out in the Award.
The building owner and their contractors must follow any requirements specified in the Award throughout the works. Failure to do so opens up the possibility of further disputes which could delay or even halt works until the issue is resolved.
It is therefore important that everyone involved is fully aware of all terms set out in the Party Wall Award before beginning.
Get Help With the Party Wall Agreement Process
Party Wall matters can be confusing for both building and adjoining owners, particularly when there is a dispute over proposed works. Seeking professional advice early can help ensure the correct procedures are followed, whether you’re planning works that may fall under the Party Wall etc. Act 1996 or have received a Party Wall Notice from a neighbour.
At Stokemont, our experienced Party Wall Surveyors can provide guidance through every stage of the process, from preparing and responding to notices through to surveyor appointments and Party Wall Awards.
Get in touch with our team today to discuss your Party Wall requirements and request a free quote.
FAQs
There is no fixed time frame for completing the Party Wall process, with how long it takes depending on factors such as:
- The nature of the proposed works.
- Whether the adjoining owner consents or dissents to the Party Wall Notice.
- How quickly the adjoining owner responds.
- Whether a single agreed surveyor or two surveyors are appointed to manage the process.
For a more detailed breakdown on time frames, read our guide on how long a Party Wall Agreement takes.
Changes may be possible after a Party Wall Agreement has been reached, but this will depend on the nature of the amendment. Where changes are proposed to works covered by a Party Wall Award, the appointed surveyor or surveyors may assess whether the existing Award is sufficient or further changes are required to ensure the interests of both owners remain protected.
Party Wall Notices are generally valid for 12 months, meaning the relevant works must begin within this period. If works do not begin within the required time frame, a new notice may need to be served before they can proceed.